AFTER PHOTOS

We, at Rochman Design Build, are so grateful for the opportunity to work on multiple projects for so many of our clients, often over the course of multiple years. But sometimes we get especially lucky and move from one project right into the 2nd , as is the case with this project. Moving from the garage and study addition on this Ann Arbor Hills colonial to the main house, this whole house remodel will include doing a whole new kitchen, mudroom, powder room and butler’s pantry on the first floor. On the 2nd floor the Rochman Design Build team will change one entire side of the house into a large and beautiful study / office, redo the bathroom, and reconfigure the master bathroom including additional work in the remainder of the master suite. Please visit this current work ‘blog’ to see the transformation.

 
210324_108.JPG
 

June 2, 2021

 
 

Zack is demolishing 3 layers of ceiling in the kitchen.

 
 

Demolition is done and the area is swept.

 
 

And here is where we turn the living room into a carpenter’s work shop :-)

June 9, 2021

The demolished kitchen, and a view of exercise area room from the kitchen.

We’ve built a temporary wall as a support structure for when the beam is removed.
The beam over this kitchen / breakfast room opening will be repaired by a much longer steel one, in order to lose the post in the middle of everything.

 
210603_408.JPG
 

The breakfast room. The hole in the floor is access to the crawlspace to put additional concrete footing to support future beam.

June 17, 2021

 
210610_417.JPG
 

Look Ma, no stairs!
Zack removed the Butler stair to 2nd floor in order to create headroom for the basement stairs.

 
210616_402.JPG
 

John get the Carpenter’s Award for the smallest wall ever framed :-)
(It’s actually a point load that we needed and John made, but the award is much more fun)

 
210617_403.JPG
 

and Mike is building out a steel beam to be able to hang a wood beam off of it.

June 23, 2021

Lots of demolition this week…

June 30, 2021

The small shed roof bedroom is in the process of being converted into a full wall height.

It will be tied into the 2 adjoining rooms to create one expansive home office.

July 15, 2021

 
 

The new office space is getting Tyveked (newly made up word? but sounds right) - aka closing it up.

The living room is having all its windows replaced.

July 22, 2021

Yep, sometimes we have to fix other remodelers problems; here we're straightening out the floor framing.
The kitchen is ready for wiring.

The new home office on the 2nd floor is getting a new French Door (exterior and interior views).
The door will have a new custom welded Juliette Balcony.

July 29, 2021

Lots going on this week too…

On the 1st floor, the kitchen is opened up with new steel and LVL beams.
And this will be the new powder room off the kitchen.

New electrical and ductwork being run for the 2nd floor study.
And while we’re at it, we might as well repair the existing sub floor in the master bath.

Although the photo doesn’t do it justice, these are the French doors off the study that will lead to the Juliette balcony mentioned before. When not being worked on, this future study occasionally doubles as a bowling alley :-)

Outside, a new retaining wall is being installed by the driveway. The perpendicular 6x6 is called a deadman (probably because it looks like something out of Hangman?) and is there to help the wall stability.

August 5, 2021

A drainpipe is being installed for the new retaining all encased in landscape liner.

And covered up with stone.

Meanwhile, on the inside it’s hard to believe that it’s finally time for insulation.

And there is A LOT to insulate...

But finally its done!
Coming up next, Drywall!

August 13, 2021

Like we said… Drywall!

 
210808_402.JPG
 

… when the shortest distance between 2 points is a straight line (lol) #lovewhenthingsareeasy

 
210816_401.JPG
 
 
210816_403.JPG
 
 
210816_407.JPG
 

August 20, 2021

September 1, 2021

Drywall and priming is complete.

 
210901_427.JPG
 

Rigid insulation is going up in the attic ceiling.

 
 

Just a cool angle view.

September 10, 2021

Exterior painting is complete.

September 16, 2021

 
210916_403.JPG
 

Hardwood floor is acclimating to the home’s humidity before installation.

September 23, 2021

 
 

Now that the wood floorboards acclimated to the home’s temperature, they’re being installed.

 
 

September 30, 2021

Meanwhile at our shop…

We’re making custom trim for the windows and doors.

October 7, 2021

The Kitchen cabinets arrived and are being installed : )

The orange waffle roll is the water proofing system that goes in first, then the floor tiles are laid.

October 15, 2021

John continues with the cabinet installation.

 
211012_403.JPG
 

As Tandem Tile continues to lay the hexagonal floor tiles in the bathroom.

The shower gets white subway tiles with a pop of aqua green, evoking the sense of calming water.

October 21, 2021

Shhh… building of shelving unit in progress ;-)

 
 
 
 
 
 

October 21, 2021

And sometimes it is almost all hands on deck as work continues throughout the house.
With John and Mike

and Brian and our newest team member, Emily.

November 5, 2021

November 13, 2021

 
 

Brian: hmm, I wonder what’s behind door #1?

November 23, 2021

While the RDB team continues to work throughout the house

Dave is just focusing on installing the book shelves, the many many bookshelves.

December 2, 2021

Finishing out the bathrooom.

 
 
 
 
 
 

December 10, 2021

The floors are uncovered, cleaned, and readied for the final sanding and coating.
(they’ll be covered once again when the painters come in)

 
 
 
 
 
 

December 22, 2021

See above parentheses : )

January 6, 2022

Painting is all done : )

January 12, 2022

Lighting is being installed throughout the house.

January 26, 2022

As is final cabinetry hardware and shelving.

February 10, 2022

Our project is complete; we will definitely miss our beyond awesome clients.
Here are just a few of the immediately after completion photos.

AFTER PHOTOS