Kitchen Remodel: Maywood
Completed December 2012.
AFTER PHOTOS
The remodel for this charming home on Maywood Ave in Ann Arbor required a make over for the kitchen and powder room to go from cute to cool.
In this project, we will be gutting the existing kitchen,
and replacing it with a new, modern-style.
We will be removing this wall between the kitchen and
the dining room, opening up the two spaces.
This powder room will also be completely re-done.
This plan shows the new kitchen and bathroom layout.
October 3, 2012
We have demoed the kitchen back to studs.
Turning around, we also removed the wall
separating the dining room and kitchen.
The small powder room has also been stripped back to studs.
October 20, 2013
The drywall is up and the first coat of paint is done.
Here at the dropped beam, we duplicated
the cove detail of the dining room
November 6, 2013
Here is lead carpenter Brian, posing quickly for
a photo before returning to work installing cabinets
The base cabinets will be be white. The blue you are seeing is a
protective film, designed to prevent scratches during installation.
November 14, 2012
The tile floor is going in. The red spaces keep the tile apart
as they are set, leaving room for grout to be added.
After the tile was finished, the cork
floor in the kitchen was installed.
November 20, 2012
This round orb is actually a ventilation hood for over the cooktop.
It came in a standard white, but we had it custom painted this
bright orange to better fit into the color palette of the finished kitchen.
November 27, 2012
The cabinets are all installed.
Another angle. Here the opening will be filled by the dishwasher.
Finally, looking toward the dining room, now open to the kitchen.
December 3, 2012
The quartz countertops are being installed.
Final countertops.
Small wall-hung sink in the powder room.
New toilet with it’s tank is hidden inside the wall.
December 12, 2012
After the countertops were done, the
tile backsplash was installed quickly after.
In both the kitchen and powder room, we installed
these decorative panels above the existing glass block.
December 13, 2012
Brian carefully measures and drills for the cabinet pull installation.
A wide angle view of the nearly finished kitchen.
The orange hood is installed and operational.
December 17, 2012
The finished powder room.
The range with the cool hood.
December 30, 2012
Our happy clients in their new space.
The new kitchen
with a cooler for drinks :-)
and the new dining room