Our clients’ 1930 Tudor style house in Lower Burns Park is welcoming and full of charm but its 2nd floor bathroom is original; and at 90 years old, it is tired and in need of serious TLC. For this project, the Rochman Design Build team will be updating and enlarging it into the adjacent bedroom in order to add a 2nd sink and provide much needed space for the teens using it. Please check this current work blog often to see how we transform the space.

April 15, 2021

You can see the need for 2 sinks... although the floor, even at 90, is still in perfect shape.

Definitely need to enlarge the space!

We’ll be expanding the bathroom into this current closet space and build a new closet elsewhere in the room.

April 22, 2021

Trash chute is built out of the bathroom window directly into a dumpster below.

Bathroom is gutted back to studs and floor joists. You can see the old galvanized pipes and knob and tube electrical wiring (which will all get replaced).

Dust door with a magnetic opening keeps our dust in our area and not our clients area.

Hardboard sheets protect the wood floors in the bedroom.

April 29, 2021

210429_402.JPG

New closet framing in adjacent bedroom;
the original closet space was captured for the new bath.

210430_400.JPG

The plumbers are preparing to set the tub in.

210430_402.JPG

And new plumbing stack in the basement

May 6, 2021

New plumbing for 1st floor powder room below remodeled bath and the built out wall for the new vanity location.

May 12, 2021

210507_12.JPG

The in-floor hot and cold water lines are in.

210507_19.JPG

As is the new electrical service panel.

210513_405.JPG

We’ve used closed cell spray foam insulation in the exterior wall.

210514_401.JPG

hanging blue board for plasterer

May 20, 2021

The tub is installed and the walls are insulated.
You can see the first coat of plaster on the new closet walls and old door location.

While drywall is in process, we’ve included two locations for future medicine cabinets.

May 27, 2021

The back wall of the shower, including the niche, has been tiled.

New tile flooring is in process.

June 2, 2021

The kids are saying “hi!” to future homeowners by burying a time capsule in the wall.

June 8, 2021

The shower / tub is in and the vanity cabinet is ready for the counter.

Clearly, the newer spouts are different sizes than the 1930s originals.
The floor tiles in slate grey is just perfect here; fresh, clean, and modern.

June 15, 2021

Our project is done! Our clients, including our teen clients, are elated :-)